FIES Workplan
This document describes the organization formed in order
to make FIES an operating instrument as quickly and efficiently as
possible assuring a high quality spectrograph will be the result with a
pleasant user interface.
The whole process is to be supervised by a PI Team. The
composition of the team is suggested here as
-
Søren Frandsen, Department of Physics and
Astronomy, Aarhus University, Chairman
-
John Telting, Nordic Optcial Telescope, La Palma,
main NOT contact person
-
Bo Lindberg, Lens-Tech, Skellefteaa, Optical engineer
-
Nikolai Piskunov, Institute of Astronomy, Uppsala
University, Scientific and Technical Advisor
-
Johannes Andersen, NOT Director, Astronomisk
Observatorium, Københavns Universitet, Coordination with NOT
The responsabilities of the PI team is to define and fix
design specification where needed, to 'godkende' construction projects
and test procedures and to organize commisioning of the complete
instrument. The PI team also forms subteams and allocate work packages
for these teams.
It is proposed to have the following work packages and
subteams at the present stage:
1. Software Team
Team members: Søren Frandsen, Jakob Clasen, John
Telting, Peter Sørensen, Johan Holmberg, Jens Viggo Clausen,
Jens Klougart and Alexandru Csete.
During a meeting at La Palma a more detailed job description
was implemented, which you will find under the status link below.
In addition an overall plan for the operation of all NOT
instruments was suggested.
Workplan:
-
Define Graphical User Interface to FIES (SF, JC,
PS, AC)
-
Write Interface to Telescope Control System (JC,
SF)
-
Write interface to CCD program BIAS (SF, JC)
-
Write interface to present FIES code (SF, AC)
-
Write interface to Standby camera (JC, PS)
-
A NOT provided sequencer, form filling, general
user interface
(PS, JC, JT)
-
Define and implement a pipeline reduction (JT, JH, JVC
)
-
Define and implement an exposure time calculator and
other preobservation tools for observers (JT, PS, SF)
-
Define and write quick look software (JT, JC, PS)
Status
2. CCD camera
Team Members: Preben Nørregaard, Anton Norup
Sørensen, John E. Andersen, Bo Lindberg and Jens Klougart
Workplan:
-
Provide drawings of FIES camera backend (JEA)
-
Order chip (PN)
-
Design and build camera box (CUO)
-
Install CCD and test it
-
Mount camera on spectrograph
-
Provide or modify a controller including a
compatible version of BIAS
Status
3. Fiber - ADC - Adaptor
Team Members: John Telting, Johannes Andersen,
Søren Frandsen, Bo Lindberg, John E. Andersen
Workplan:
-
Define parameters (number of fibers etc.)
-
Design Atmospheric Dispersion Corrector
-
Build mechancis at IFA
-
Build fiber units at Lens-Tech
-
Install at the NOT
Status
4. New Building - Thermal Control
Team Members: John Telting, Søren Frandsen, Bo
Lindberg, Peter Brandt, Thomas Augusteijn and John E. Andersen
Workplan:
-
Design building and make drawings
-
Get the permissions to build it
-
Contract with building companies
Status